A project material is an inventory item defined in Acumatica ERP as either of the following:
You need to accurately track materials purchased for projects to avoid delays, minimize costs, and ensure the availability of necessary resources at each stage of the project.
On the Project Materials (PM306500) form, you can manage material requirements by project task while keeping costs tied to the project budget.
Each material listed on the form is linked to the project budget key, so its actual costs stay aligned with the related budget lines and commitments. You can allocate stock items, purchase items to be delivered to a warehouse, or have items drop-shipped to the project site, and you can track the materials at each stage of fulfillment.
Each material line represents one material requirement—that is, a specific stock or non-stock item requiring a purchase receipt and shipment and the quantity needed for a specific project task. In each material line, you can view the project task, account group, and cost code. This makes it easy to track each material’s costs against the corresponding budget line and monitor commitments and actual costs in the project budget.
Managing a project’s materials consists of the following general steps:
In addition to the general workflow of project material management in Acumatica ERP, depending on your company’s business processes, you may have the following general cases of using materials for projects:
If some project inventory is left unused for a completed project, you need to transfer all the leftover material back to the free stock. For more information, see Project Inventory Tracking: Mass Processing.
The following diagram illustrates the material management flow in projects for all commitments and shows how costs are recorded to the project budget depending on the type of document being processed.
The system tracks subcontracts as commitments to projects if the Internal Cost Commitment Tracking check box is selected on the Projects Preferences (PM101000) form. For details about subcontracts, see Subcontracts: General Information.