This generic inquiry form is available if the Extended Financial Data Collection feature is enabled on the Enable/Disable Features (CS100000) form.
The form toolbar has only standard buttons.
In this area, you select the project whose data you want to view in the table and the date through which data is calculated.
In the table, you can see how quantities and unit rates influence project cost and revenue variances. This information is presented as of the selected date, including for projects with incomplete tasks. Each row represents a cost or revenue budget line of the project.
The table toolbar has only standard buttons.
The columns below contain values you can compare to see the difference between the budgeted and actual values. Column colors make revenue and expenses easy to spot:
Revised Contract Amount - Billed Amount to Date
(Revised Contract Quantity - Billed Quantity to Date) * Revised Contract Amount / Revised Contract Quantity
Revised Contract Quantity
Billed Variance Amount - Billed Variance Amount by Quantity
Actual Total Cost (Quantity to Date) / Revised Budgeted Cost (Quantity)
Revised Budgeted Cost (Quantity)
Actual Total Cost (Amount to Date) - Revised Budgeted Cost (Amount)