You can use engineering change control functionality only if the Engineering Change Control feature in the Manufacturing group of features is enabled on the Enable/Disable Features (CS100000) form.
In this topic, you will read about ECC in Acumatica ERP.
Engineering change control provides the following abilities:
The following restrictions apply if the Require ECR/ECO for New BOM Revisions check box is selected on the BOM Preferences (AM101000) form:
If you organization has a small engineering team, you may find it undesirable to create an engineering change request as a prerequisite to creating an engineering change order. The team may want to eliminate the extra step of reviewing and generating the ECO and avoid storing unnecessary data in the system.
To allow the direct creation of ECOs, you clear the Require ECR before Creating ECO check box on the BOM Preferences (AM101000) form. After that, you can create an ECO directly on the Engineering Change Order (AM215000) form by clicking Add New Record on the form toolbar.
Once the check box has been cleared, we do not recommend selecting it again because this may cause the engineering change control functionality to work improperly.
In the following diagram, you can view the workflow of engineering change control with the following settings on the BOM Preferences (AM101000) form:
To initiate changes in an existing bill of material, you perform the following steps: